Verdugo Projects

Central Plant #1 Expansion

Description

This project anticipates expanding the Central Plant from its current approximate 500-ton capacity to an approximate 1500 ton capacity in anticipation of the construction of the Science Building and the Instructional Building & Conference Center (IBCC). The existing chillers lack both the capacity and efficiency to provide the necessary cooling for these two new buildings.

Updates

  • Reviewing potential chilled water pathways presented by the Design Team
  • Site walk with selected Design Team and Construction Manager completed on 10/14/2020
  • Conducted Initial Planning Discussions Meeting with selected design team on 10/14/2020
  • Post-selection Introductory Meeting held on 09/30/2020 with selected Design Team
  • GCC has selected Affiliated Engineers (AEI) as the Design Team for the project
  • Review of proposals in progress
  • Site walk conducted on 8/12/2020 to understand piping route underneath Auditorium to the Science Building
  • Proposals from prospective design teams due 8/7/2020
  • GCC posted RFI responses on 7/30/2020
  • Mandatory Job Walk of site conducted on July 20, 2020

Status

Designing 12%

Project Team

Project Manager Joseph Lutz, Gafcon, Inc.
General Contractor TBD
Architect of Record TBD
Inspector of Record TBD