Verdugo Campus: Jan 27 (F) – Planned crane usage activities for PE Student Locker Building Project to take place over a period of two weeks. Vehicles will enter the site via Lot E entrance on Mountain St.
Verdugo Projects
Central Plant #1 Expansion
Description
This project anticipates expanding the Central Plant from its current approximate 500-ton capacity to an approximate 1500 ton capacity in anticipation of the construction of the Science Building and the David Viar Performing and Media Arts Center. The existing chillers lack both the capacity and efficiency to provide the necessary cooling for these two new buildings.
Updates
Project Completion: Under Construction – 86%
Status Update As of: 1/24/2023 (Last two week’s activities in bold)
- 01/18: Transformer mounting activity at panel completed
- 01/24: Chiller end cap torquing activities
- Existing cooling tower media pressure washed
Status
Project Team
Project Manager | Jim Youngblood, Gafcon, Inc. |
Construction Manager | John Theis,DPR Construction |
Architect of Record | Sean Rosebrugh,HMC Architects |
Project Design Engineer | Steve Yanke,AEI |
Inspector of Record | TBD |