Verdugo Campus: Dec 06 (T) – Dec 14 (W) – Trenching activities near south Auditorium Building entrance for Central Plant 1 Expansion Project. Access to southern double-door exit impacted; signage for alternative paths of travel is provided.
Verdugo Campus: Dec 09 (F) – Steel delivery in Lot H for Central Plant 1 Expansion Project to take place at 7:00 AM. Trucks will enter the site via the Circle Drive gate entrance on N. Verdugo Rd; area will be taped off.
Verdugo Campus: Dec 13 (T) – Dec 14 (W) – Crane mobilization and steel placement for Central Plant 1 Expansion Project. Access to Lot H parking will be impacted.

District-wide Projects

Safety & Security

Description

All existing classrooms and lab spaces (more than 200 total), along with various administrative office areas, will be retrofitted with upgraded security measures to improve safety district-wide. These measures include communication and visual systems.

Update

Project Completion: On Hold as of 3/1/2021

Status

In Progress 70%

Project Team

Project Manager Silva Sorkazian, Glendale Community College
General Contractor TBD
Architect of Record Various
Project Consultant RAS Consulting & Investigations
Inspector of Record TBD