Safety & Security – Project Update History

Status Update As of: 3/1/2021 – Project has been put on hold

  • 3/1/2021: 100% CD document review completed

Status Update As of: 2/15/2021

  • No update

Status Update As of: 2/1/2021

  • Development of RFP specifications in progress

Status Update As of: 1/4/2021

  • Door hardware review in progress
  • Milestone schedule provided by Design Consultant under review
  • Security camera location recommendations under review

Status Update As of: 12/21/2020

  • No update

Status Update As of: 12/7/2020

  • First phase of design documents for Garfield and Montrose campuses under review
  • Security drawing draft for Verdugo Campus under review
  • RAS System specifications review meeting completed on 12/8/2020
  • Site tour with the Design Consultant conducted on 11/12/2020
  • RFP document development in progress
  • GCC Design Consultant assisting with development of draft RFP to send to potential integrators
  • RAS named GCC Design Consultant for security cameras for integrators to design and implement security system
  • Security Camera project pending finalization of vendor on-boarding
  • Due diligence conducted on vendor via site visit