Verdugo Projects

San Gabriel First Floor ‐ Disabled Students Programs and Services (DSPS) Renovation

Updates

Project Completion: Construction – 100%

  • 12/21/2023: DSA Certification of Compliance issued
  • 11/29/2023: PROJECT COMPLETE. NO MORE UPDATES.
  • 11/8/2023: No update
  • 9/5/2023: Issued final DSA payment for closeout.
  • 7/18/2023: SS follow up with DSA re: closeout

Description

Space on the first floor of the San Gabriel Building is being designed to become the campus’ new office for Disabled Students Programs and Services (DSPS). This location on the ground floor near the Access bus stop improves access for students with mobility challenges. The project expands testing and assessment space, as well as office space, for DSPS personnel.

Status

Construction 100%

Project Team

Project Manager Silva Sorkazian, Glendale Community College
General Contractor TBD
Architect of Record James Moreto, MMA Architects
Inspector of Record Tony Castiglioni, VIS Vital Inspection Services Inc.