Verdugo Campus: Saturday (10/2) to Friday (10/15) – Lane closure of Verdugo Rd. near the walkway bridge area to accommodate utility connection activities to City utility lines for the New Science Building Project to take place from 7:00 AM to 4:00 PM for a period of 12 days. Alternative pathway will be provided for pedestrians to be routed up the walkway bridge; this activity will minimally impede traffic entering or exiting the campus.
Verdugo Campus: Friday (10/15) – Concrete repair for the Sierra Vista Building walkway to take place from 7:00 AM to 3:00 PM. Concrete trucks will enter via Mountain St.; flag persons will be stationed in the area to ensure pedestrian safety and there will be minimal impedance on traffic entering or exiting the campus.
Garfield Campus: Saturday (10/16) – Concrete sawcutting activities to take place near the Parent Support Center, mechanical enclosure, and project construction trailer areas. Barriers will be stationed in the area to ensure traffic and site safety; activities will minimally impede traffic entering or exiting the campus.
Verdugo Campus: Week of Monday (10/25): Assembly of fence to safely enclose the following locations in Parking Lot B – Northwest corner of parking lot (near CA-2 freeway) to house large-size New Science Building (NSB) façade mock-ups and a select area of parking spaces near the hillside to store soil pile-up from the NSB project; the areas will remain fenced in until the Spring of 2023. These activities will impact parking for Parking Lot B.

Verdugo Projects

Instructional Building & Conference Center (IBCC)

Description

The new multi-story Instruction Building & Conference Center (IBCC) will be a collaborative and cross-disciplinary environment housing classrooms; studio space for music, dance, film, television, and electronic media; performance space; faculty offices; and a conference center that will accommodate events of many types and sizes.

Glendale Community College’s strong programs in the performing arts are housed in aging and insufficiently sized facilities. The IBCC, being adjacent to both the Verdugo Gym and the Auditorium, will support collaboration and sharing of resources between these facilities and their programs. The Performance Plaza builds on Plaza Vaquero to accommodate the student population with outdoor places for gathering and engaging in activities at the center of campus.

Updates

Project Completion: Designing – 25%

Status Update As of: 10/04/2021 (Last two week’s activities in bold)

  • Week of 10/4: Project schedule review
  • 10/7: Underground investigation activities
  • 10/8: Site walk for sound mitigation wall complete
  • 10/14: Target date for project logistics review with General Contractor

Status

Designing 25%

Project Team

Project Manager Jim Youngblood, Gafcon, Inc.
General Contractor Austin Wheelon, PCL Construction Services, Inc.
Architect of Record Kim Patten, Steinberg Hart
Inspector of Record TBD

Video