Verdugo Campus: Dec 06 (T) – Dec 14 (W) – Trenching activities near south Auditorium Building entrance for Central Plant 1 Expansion Project. Access to southern double-door exit impacted; signage for alternative paths of travel is provided.
Verdugo Campus: Dec 09 (F) – Steel delivery in Lot H for Central Plant 1 Expansion Project to take place at 7:00 AM. Trucks will enter the site via the Circle Drive gate entrance on N. Verdugo Rd; area will be taped off.
Verdugo Campus: Dec 13 (T) – Dec 14 (W) – Crane mobilization and steel placement for Central Plant 1 Expansion Project. Access to Lot H parking will be impacted.

District-wide Projects

Technology

Description

This project includes moving the College’s primary system software to a more robust PeopleSoft system, along with various upgrades to the College’s overall academic and administrative system software.

Update

Project Completion: 100% Completed as of – 12/20/2021

Status

Complete 100%

Project Team

Project Manager Various
General Contractor Various
Architect of Record Various
Inspector of Record Various