Verdugo Campus: Monday, 3/8 – Concrete pour for Verdugo Gym Expansion Project site Northwest Retaining Stem Wall to take place from 6:00 AM to 3:00 PM. Concrete trucks will enter via N. Verdugo Rd.; flag persons will be stationed in the area and there will be minimal impedance on traffic entering or exiting the campus.

District-wide Projects

Energy Conservation

Description

This is a series of projects to enhance the energy conservation programs on campus. As envisioned the project will include up-date/replacement of old outdated HVAC Systems, Replacement of various inefficient exterior windows (i.e. Administration building) with new energy-efficient multi-glazed windows, and the installation of a new centralized electronic HVAC control system.

Update

Project Completion: 100% Completed as of 12/31/2020

Status Update As of: 12/7/2020

  • Administration Window Replacement Project (AWRP)
    • Project has been completed
    • Exterior door hardware, wiring, and staining in progress
    • Final Punch List inspection on 10/26/2020
    • Closing out of Punch List items in progress – window and door items walk-through completed on 09/25/2020
    • Overall Project 97% complete
    • Phase 5 to begin week of 08/17/2020
    • Phase 4 currently in progress
    • Phase 3 complete
    • Phase 1 and Phase 2 complete

Status

Completed 100%

Project Team

Project Manager Mark Edwards, BRJ & Associates, LLC
General Contractor Jimi Chae, Green Contractor Studio, Inc.
Architect of Record Melvin Enriquez, 19six Architects
Inspector of Record Tony Castiglioni, VIS Vital Insepction Services Inc.