The 2025-2035 Facilities Strategic Plan – DRAFT as presented to the Board of Trustees on July 26, 2024
Verdugo Projects
Welding Shop Alteration, Tongva Building (fka Aviation/Art Building) – Project Update History
Project Completion: Completed – 100%
Status Update As of: 4/5/2021
- Bypass inverter installation completed and inspected
- Final punch-list items signed off by IOR
- Architect item finalization and completion review in progress
Status Update As of: 3/15/2021
- IOR open items list completed
- Final punchlist items nearing completion
Status Update As of: 3/1/2021
- Received DSA approval for fire alarm upgrades related to identified punchlist items
Status Update As of: 2/15/2021
- No update
Status Update As of: 2/1/2021
- Fire alarm close-out documents for the Tongva Building (AA Building) and Advanced Technology Center approved
- Heater strip was installed
- 2/01/2021: Anticipated completion of electrical connections to heat strips for the office and classroom
- 2/01/2021: Anticipated completion of insulation of HVAC split system on building roof
Status Update As of: 1/4/2021
- No update
Status Update As of: 12/21/2020
- Fire Alarm testing complete
- Architect and Inspector issued APEX Punchlist; corrections in progress
Status Update As of: 12/7/2020
- Electrical room cooling in progress
- Punch list walk with Architect and Engineer completed on 12/7/2020
- Welding booth snorkel connection near completion
- AT Building fire alarm system test completed
- Start-up and testing of units in progress
- Punchlist items for fire sprinklers in classrooms and offices complete
- Review of revised proposals for heating in classrooms and offices and air conditioning for electrical room
- Inspector of Record began work on punch list items week of 10/19/2020
- Proposed bracket detail for welding booth bracing approved
- Finalizing of conduit rack, installation of snorkels, and canopy installation in progress
- Permanent power to Welding Shop completed – breakers received in week of 10/05/2020; breaker installation included planned power shutdown
- Electric conduit racking system in progress
- Temporary power installed to welding booths and classroom
- Welding booths and equipment received, installation in progress; Welding booth assembly complete
- High voltage termination complete
- Electrical feed to new electrical room to be terminated
- Fire Alarm System 90% installed; Preliminary electrical installation finalized
- Existing welding equipment relocated from old Welding Shop to renovated Welding Shop in Aviation/Art Building on 8/19/2020
- Electrical panels and switches delivered on 7/31/2020; the feed to the units is in progress
- Electric low voltage to be completed week of 8/3/2020
- Dust collector unit installed; DC fan to be installed week of 8/3/2020
- AA-Poured 30+/- yds. of concrete for Dust Collector and mechanical pad
- ATC-Fire Alarm and device testing complete
- Target completion: August 28, 2020