Verdugo Projects

San Rafael Renovation – Second Floor – Project Update History

Status Update As of: 12/7/2020

  • Lockers removed from Adjunct Faculty space
  • Cubicle furniture reorganized for CalWorks and Student Equity programs
  • Punch list item corrections closed out
  • Inspector of Record to begin final DSA closeout process
  • Outstanding items Punch List Walk conducted on 9/09
  • College Departments completed moving in week of 8/24/2020
  • Final punch list items nearing completion
  • Proposed move in schedule communicated to User Groups and College Leadership week of 8/3/2020
  • Final closeout items in progress; Furniture-IT-AV-Electrical installation complete week of July 20, 2020
  • Target Move-in Date: Last week of August 2020