The 2025-2035 Facilities Strategic Plan – DRAFT as presented to the Board of Trustees on July 26, 2024
Verdugo Projects
San Rafael Renovation – Second Floor – Project Update History
Status Update As of: 12/7/2020
- Lockers removed from Adjunct Faculty space
- Cubicle furniture reorganized for CalWorks and Student Equity programs
- Punch list item corrections closed out
- Inspector of Record to begin final DSA closeout process
- Outstanding items Punch List Walk conducted on 9/09
- College Departments completed moving in week of 8/24/2020
- Final punch list items nearing completion
- Proposed move in schedule communicated to User Groups and College Leadership week of 8/3/2020
- Final closeout items in progress; Furniture-IT-AV-Electrical installation complete week of July 20, 2020
- Target Move-in Date: Last week of August 2020