Verdugo Campus: Thursday (11/25) through Sunday (11/28) – Domestic water line depression activities at the Verdugo Gym Expansion Project site to take place over a period of 4 days. These activities will begin at 7:00 AM each day; there will be minimal impedance on traffic entering or exiting the campus.
Verdugo Campus: Saturday (12/18) – Planned power outage for temporary power extension activities to the New Science Building Project site to take place at 6:00 AM for a duration of 12 to 16 hours. Generators will be provided for necessary Police systems, Administration Building IT servers, and Gym sporting events. Flag persons and barricades will be stationed between the New Science Building and Sierra Vista area for pedestrian safety and vehicle traffic; there will be minimal impedance on traffic entering or exiting the campus.

Verdugo Projects

San Gabriel Renovations‐Math Department Relocation – Project Update History

Status Update As of: 11/01/2021

  • Week of 11/1: Anticipated charging cart station acquisitions
  • Beta test of Math and Science computer labs functionality for wireless configuration complete; coordinating compatible furniture options in progress

Status Update As of: 10/18/2021

  • Week of 10/18: Target timeline for charging cart station acquisition
  • Wireless beta test development discussions and feedback with GCC IT Department in progress

Status Update As of: 10/04/2021

  • No update

Status Update As of: 9/20/2021

  • No update

Status Update As of: 9/1/2021

  • November 2021: Target date for San Gabriel wireless beta test recommendations

Status Update As of: 8/2/2021

  • No Update

Status Update As of: 7/19/2021

  • Awaiting design progression and technical comments for beta testing

Status Update As of: 6/21/2021

  • Planning of 3 phase WiFi beta testing in progress

Status Update As of: 5/17/2021

  • No update

Status Update As of: 5/03/2021

  • No update

Status Update As of: 4/19/2021

  • No update

Status Update As of: 4/5/2021

  • No update

Status Update As of: 3/15/2021

  • No update

Status Update As of: 3/1/2021 (Last two week’s activities in bold)

  • Preparations for WIFI beta test in progress

Status Update As of: 2/15/2021

  • No update

Status Update As of: 2/1/2021

  • No update

Status Update As of: 1/4/2021

  • No update

Status Update As of: 12/7/2020

  • WiFi beta test design in progress; target date for completion – end of June 2021
  • 1/11/2021: Target date to receive back-check of Constructibility Review comments and updated cost estimate from Construction Manager
  • 12/18/2020: 90% Construction Documents and review comments received

Status Update As of: 12/7/2020

  • 90% Construction Documents and review comments anticipated 12/18/2020
  • 50% Construction Documents and specifications received from the Architect
  • The Architect completed door survey and provided cost estimate
  • AT107 under consideration as model for wireless design conversion
  • Target date for DSA submission: 12/18/2020
  • 50% Construction Documents submission in progress; target date 11/13/2020
  • Constructibility and cost estimate verification reviews submitted on 10/23/2020
  • Requesting proposal for wireless network engineering design in process
  • Information Technology System meeting to be scheduled related to prospective wireless option approach
  • Scheduling cost estimate review with General Contractor after receipt of Design Document set
  • Conducted presentation for User Groups on 09/25/2020
  • General Contractor provided updated cost estimate in week of 09/21/2020
  • Architect design schedule revised to show continuous effort through DSA submission –
  • Project Manager scheduling next User Group Meeting to review Design Development progress by the Architect
  • General Contractor provided updated cost estimate on 9/08 after value engineering cost exercise with team
  • San Gabriel 2nd Floor Renovation design efforts restarted week of 8/10/2020
  • Architect design schedule anticipates completion of Design Development (DD) by end of September 2020
  • Construction Manager (CM) to issue project schedule for architects to target Design Development restart date
  • Project Manager (PM) and CM provided 25% DD scope/estimate reconciliation
  • Architect submitted 25% Design Development (DD) plans to PM and CM