San Gabriel First Floor ‐ Disabled Students Programs and Services (DSPS) Renovation – Project Update History

Status Update As of: 1/24/2023

  • Pending Division of the State Architect (DSA) certification

Status Update As of: 1/10/2023

  • No update

Status Update As of: 11/15/2022

  • No update

Status Update As of: 11/01/2022

  • Completion of final punch-list items and closeout in progress

Status Update As of: 10/04/2022

  • Water testing activities in progress

Status Update As of: 09/06/2022

  • Punchlist completion items in progress

Status Update As of: 08/23/2022

  • No update

Status Update As of: 08/10/2022

  • Week of 8/09: Target completion of ceiling tile replacement activities
  • Punch list item completion in progress

Status Update As of: 07/19/2022

  • 7/06: Fire Alarm testing completed
  • 7/22: User group move in completed

Status Update As of: 07/05/2022

  • 6/30: Furniture delivery complete

Status Update As of: 06/07/2022

  • 6/30: Target date for second furniture installation activities

Status Update As of: 05/17/2022

  • No update

Status Update As of: 05/03/2022

  • 5/13: Target date for Punch Walk
  • 5/15: Target substantial completion
  • June: Target furniture delivery timeline

Status Update As of: 04/18/2022

  • IT Department coordination activities in progress
  • Furniture delivery schedule and items review in progress

Status Update As of: 04/04/2022

  • 4/29: Updated target date for substantial completion of project

Status Update As of: 03/21/2022

  • Finalizing of Owner Furnished Owner Installed (OFOI) AV/IT items

Status Update As of: 03/07/2022

  • 4/29: Updated substantial completion date
  • Updated vendor quote for furniture order in progress

Status Update As of: 02/07/2022

  • Week of 2/07: Target timeline to receive furniture vendor quote
  • 2/07: Framing delivery received
  • 2/18: Target turnover date for SG 135 Anatomy Lab
  • Demolition activities completed

Status Update As of: 01/10/2022

  • 1/05: Start of scheduled Owner, Architect, and Contractor meetings
  • 1/07: Start of demolition activities of project area

Status Update As of: 12/20/2021

  • 12/14: Project Preconstruction Kickoff Meeting

Status Update As of: 12/06/2021

  • December 2021: Notice of intent to award for selected General Contractor for Board of Trustees’ approval
  • Spring 2022: Target completion date of project

Status Update As of: 11/15/2021

  • Bid due date for project moved to November 19, 2021
  • Door hardware review in progress

Status Update As of: 11/01/2021

  • 11/2: Project site walk completed
  • 11/11: Due date for project bids
  • 11/16: Target date of Board of Trustees approval
  • Coordination of Furniture, Fixtures, and Equipment (FF&E) and Electric activity items in progress

Status Update As of: 10/18/2021

  • No update

Status Update As of: 10/04/2021

  • 10/7: Target date for advisement on Addendum 1 to Division of State Architect (DSA) approved plans

Status Update As of: 9/20/2021

  • Development of Furniture, Fixtures, and Equipment (FF&E) items and procedures in progress

Status Update As of: 9/1/2021

  • 8/25: User group meeting completed
  • Documentation of storage needs in progress
  • Architect provision of Division of State Architect (DSA) inspection requirements in progress

Status Update As of: 8/2/2021

  • No Update

Status Update As of: 7/19/2021

  • No Update

Status Update As of: 6/21/2021

  • 6/18: Received DSA approval of project plans

Status Update As of: 5/17/2021

  • No update

Status Update As of: 5/03/2021

  • No update

Status Update As of: 4/19/2021

  • Fire alarm upgrade drawings submitted to DSA; review comments in progress

Status Update As of: 4/5/2021

  • Fire alarm upgrade drawings submission to DSA in progress

Status Update As of: 3/15/2021

  • Fire alarm upgrade design in progress

Status Update As of: 3/1/2021

  • Awaiting DSA comments and approval of fire alarm upgrades

Status Update As of: 2/15/2021

  • No update

Status Update As of: 2/1/2021

  • 2/02/2021: DSA backcheck appointment

Status Update As of: 1/4/2021

  • No update

Status Update As of: 12/21/2020

  • Final ADA comments received from DSA; Architect back-check comments in progress

Status Update As of: 12/7/2020

  • DSA Notice of Progress letter received; plan review in progress
  • DSA intake of revised plans submitted 10/28/2020
  • Accessibility upgrades design in progress
  • Awaiting updated redesign; Target date for new DSA submission: Mid-October
  • Revised plans to be submitted to DSA on September 4, 2020 for 2 week expedited review
  • Anticipating response of DSA extension status
  • Project document and DSA comments have been shared with San Gabriel Level 2 Math Design Team
  • Project will be advertised for bid upon receipt of DSA approval of raised floor redesign
  • Target Completion date was Fall 2020; delayed due to COVID-19; completion date Summer 2021