Verdugo Projects
San Gabriel First Floor ‐ Disabled Students Programs and Services (DSPS) Renovation – Project Update History
Status Update As of: 1/24/2023
- Pending Division of the State Architect (DSA) certification
Status Update As of: 1/10/2023
- No update
Status Update As of: 11/15/2022
- No update
Status Update As of: 11/01/2022
- Completion of final punch-list items and closeout in progress
Status Update As of: 10/04/2022
- Water testing activities in progress
Status Update As of: 09/06/2022
- Punchlist completion items in progress
Status Update As of: 08/23/2022
- No update
Status Update As of: 08/10/2022
- Week of 8/09: Target completion of ceiling tile replacement activities
- Punch list item completion in progress
Status Update As of: 07/19/2022
- 7/06: Fire Alarm testing completed
- 7/22: User group move in completed
Status Update As of: 07/05/2022
- 6/30: Furniture delivery complete
Status Update As of: 06/07/2022
- 6/30: Target date for second furniture installation activities
Status Update As of: 05/17/2022
- No update
Status Update As of: 05/03/2022
- 5/13: Target date for Punch Walk
- 5/15: Target substantial completion
- June: Target furniture delivery timeline
Status Update As of: 04/18/2022
- IT Department coordination activities in progress
- Furniture delivery schedule and items review in progress
Status Update As of: 04/04/2022
- 4/29: Updated target date for substantial completion of project
Status Update As of: 03/21/2022
- Finalizing of Owner Furnished Owner Installed (OFOI) AV/IT items
Status Update As of: 03/07/2022
- 4/29: Updated substantial completion date
- Updated vendor quote for furniture order in progress
Status Update As of: 02/07/2022
- Week of 2/07: Target timeline to receive furniture vendor quote
- 2/07: Framing delivery received
- 2/18: Target turnover date for SG 135 Anatomy Lab
- Demolition activities completed
Status Update As of: 01/10/2022
- 1/05: Start of scheduled Owner, Architect, and Contractor meetings
- 1/07: Start of demolition activities of project area
Status Update As of: 12/20/2021
- 12/14: Project Preconstruction Kickoff Meeting
Status Update As of: 12/06/2021
- December 2021: Notice of intent to award for selected General Contractor for Board of Trustees’ approval
- Spring 2022: Target completion date of project
Status Update As of: 11/15/2021
- Bid due date for project moved to November 19, 2021
- Door hardware review in progress
Status Update As of: 11/01/2021
- 11/2: Project site walk completed
- 11/11: Due date for project bids
- 11/16: Target date of Board of Trustees approval
- Coordination of Furniture, Fixtures, and Equipment (FF&E) and Electric activity items in progress
Status Update As of: 10/18/2021
- No update
Status Update As of: 10/04/2021
- 10/7: Target date for advisement on Addendum 1 to Division of State Architect (DSA) approved plans
Status Update As of: 9/20/2021
- Development of Furniture, Fixtures, and Equipment (FF&E) items and procedures in progress
Status Update As of: 9/1/2021
- 8/25: User group meeting completed
- Documentation of storage needs in progress
- Architect provision of Division of State Architect (DSA) inspection requirements in progress
Status Update As of: 8/2/2021
- No Update
Status Update As of: 7/19/2021
- No Update
Status Update As of: 6/21/2021
- 6/18: Received DSA approval of project plans
Status Update As of: 5/17/2021
- No update
Status Update As of: 5/03/2021
- No update
Status Update As of: 4/19/2021
- Fire alarm upgrade drawings submitted to DSA; review comments in progress
Status Update As of: 4/5/2021
- Fire alarm upgrade drawings submission to DSA in progress
Status Update As of: 3/15/2021
- Fire alarm upgrade design in progress
Status Update As of: 3/1/2021
- Awaiting DSA comments and approval of fire alarm upgrades
Status Update As of: 2/15/2021
- No update
Status Update As of: 2/1/2021
- 2/02/2021: DSA backcheck appointment
Status Update As of: 1/4/2021
- No update
Status Update As of: 12/21/2020
- Final ADA comments received from DSA; Architect back-check comments in progress
Status Update As of: 12/7/2020
- DSA Notice of Progress letter received; plan review in progress
- DSA intake of revised plans submitted 10/28/2020
- Accessibility upgrades design in progress
- Awaiting updated redesign; Target date for new DSA submission: Mid-October
- Revised plans to be submitted to DSA on September 4, 2020 for 2 week expedited review
- Anticipating response of DSA extension status
- Project document and DSA comments have been shared with San Gabriel Level 2 Math Design Team
- Project will be advertised for bid upon receipt of DSA approval of raised floor redesign
- Target Completion date was Fall 2020; delayed due to COVID-19; completion date Summer 2021


