TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST TEST

Garfield Projects

Garfield Parking & Landscape – Project Update History

8/26/2024:

  • Closeout activities in progress

Project Completion: Construction – 99%

Status Update As of: 2/7/2024:  No Update

Status Update As of: 1/31/2024: Final test & balance report is in and successful

Status Update As of: 1/24/2024: Received Tab report and DSA certification

Status Update As of: 1/17/2024: Wed Jan 17 TAB testing in progress

Status Update As of: 1/24/2023

  • Garfield Property and Landscape Construction 
    • Coordination of striping for pathway between Mariposa and Tropico Buildings in progress
    • Pending Notice of Termination (NOT) document from CA State Stormwater Board
  • Somerset Modulars
    • Pending Division of the State Architect (DSA) certification

Status Update As of: 1/10/2023

  • Garfield Property and Landscape Construction 
    • Bioswale area maintenance in progress
  • Somerset Modulars
    • Modulars in place and are in use

Status Update As of: 11/15/2022

  • Garfield Property and Landscape Construction 
    • 11/15: Garfield Parking and Somerset Complex Ribbon Cutting Ceremony held
  • Somerset Modulars
    • Handrail painting coordination in progress
    • Final install for fire alarm exterior horn strobes in progress

Status Update As of: 11/01/2022

  • Garfield Property Acquisition and Parking Construction 
    • 11/15: Planned date for project Ribbon Cutting ceremony
    • Hydroseeding activities for green spaces under Storm Water Pollution Protection Plan (SWPPP) review
  • Somerset Modulars
    • 11/01 – 11/03: Target timeline for completing fire alarm system activities
    • 11/07: Target date for final move activities to modulars

Status Update As of: 10/04/2022

  • Review and confirmation of Punchlist item completion in progress

Status Update As of: 09/06/2022

  • 9/02: Electrical breaker installation completed

Status Update As of: 08/23/2022

  • Pull box installation in progress
  • Project punchlist items review in progress
  • Beneficial Occupancy document received for Parking Lot

Status Update As of: 08/10/2022

  • Lighting poles installation activities in progress

Status Update As of: 07/19/2022

  • 7/18: Water and Irrigation Meter certification completed
  • 7/18 – 7/19: Modulars delivered to site
  • 7/29: Scheduled date for final inspection
  • Regrading activities for drainage functionality of area in progress

Status Update As of: 07/05/2022

  • 7/18: Target date of Allied Health Modular delivery

Status Update As of: 06/07/2022

  • 6/27: Allied Health Modular’ delivery
  • 6/28: Target date for Punch List walk
  • 6/30: Target date of substantial completion

Status Update As of: 05/17/2022

  • 6/27: Target date for modular delivery and installation

Status Update As of: 05/03/2022

  • 5/18: Target date for asphalt placement
  • 5/30: Target date for substantial completion Punch Walk

Status Update As of: 04/18/2022

  • 5/18: Revised target completion date
  • Trenching and telecommunication line installation activities complete

Status Update As of: 04/04/2022

  • Scheduling of user group meeting in progress
  • Project schedule review and update in progress
  • Coordination and planning activities for electrical power and plumbing to modulars in progress

Status Update As of: 03/21/2022

  • 4/15: Target date for completion
  • 4/16: Target date for vendor to deliver modulars

Status Update As of: 03/07/2022

  • 4/06/2022: Updated target substantial completion date

Status Update As of: 02/07/2022

  • 2/07: Temporary fire alarm connections in progress
  • 3/15: Target date for project completion

Status Update As of: 01/10/2022

  • Solar conduit path and trenching activities in progress

Status Update As of: 12/20/2021

  • No update

Status Update As of: 12/06/2021

  • Project approved by Division of the State Architect (DSA)
  • End of January 2022: Target date for substantial completion
  • Spring 2022: Target date for user use

Status Update As of: 11/15/2021

  • Electrical activities and system requirements of prospective equipment under review

Status Update As of: 11/01/2021

  • Awaiting Division of State Architect (DSA) approval to proceed with construction

Status Update As of: 10/18/2021

  • 10/8: Final acquired property demolished
  • 10/15: Lab testing proposals received
  • Scheduled meeting with City of Glendale Director of Public Works for sidewalk maintenance

Status Update As of: 10/04/2021

  • 9/27: HAZMAT survey completed; additional demolition activities to proceed pending final survey results
  • Interior Garfield Campus and construction site fence addition in progress
  • Processing of city permits and construction documents for telecommunications in progress
  • Division of State Architect (DSA) comments and backcheck appointment in progress

Status Update As of: 9/20/2021

  • 9/23: Target date for additional HAZMAT survey
  • Project plans in Division of State Architect (DSA) review; target date of response by end of September
  • Demolition processes nearing completion
  • Temporary Verizon generator removal complete
  • Curb painting for 3-min Loading Zone for Parent Support Center complete

Status Update As of: 9/1/2021

  • 8/28: Asphalt removal near Parent Support Center complete
  • Project site demolition: 70% complete
  • Project documentation under DSA review; anticipated response date – 9/30
  • Final property acquisition negotiation procedures in progress
  • Temporary relocation of Verizon generators approval processes and procedures under review

Status Update As of: 8/2/2021

  • 7/28: DSA Intake
  • 7/31: 100% DSA Drawing-Spec Package received
  • 8/2: Start of demolition of selected properties
  • Power disconnection effort complete; soft disconnection of water complete
  • Potential telecommunication utilities relocation options under review

Status Update As of: 7/19/2021

  • 7/12: HAZMAT surveys and abatement of remaining vacant properties
  • Week of 7/19: Target timeline for demolition activities
  • Week of 7/19: Target completion timeline for tree and vegetation removal
  • Disconnection of utilities of selected properties in progress

Status Update As of: 6/21/2021

  • 6/14: Architect presentation of Schematic Design package completed
  • 6/17: Soil testing completed
  • Week of 6/21: Target date to receive boring and percolation test findings
  • Week of 6/21: Site walk with vendor to confirm tree and vegetation removal and schedule
  • Week of 6/28: Anticipated receipt of final report
  • 6/28: Start of abatement procedure
  • Finalizing eminent domain negotiations

Status Update As of: 5/17/2021

  • 5/19: HAZMAT abatement survey conducted
  • Flyer for community notification in progress

Status Update As of: 5/03/2021

  • 5/04: Completed formal Kick-Off meeting with Design Build Entity – Menemsha/MMA Architects
  • Contract review discussions and pre-demolition considerations in progress

Status Update As of: 4/19/2021

  • 4/06: Completed interview of prospective Design Build Entity (DBE)
  • 4/19: Completed introduction and coordination meeting of selected DBE – Menemsha/MMA Architects

Status Update As of: 4/5/2021

  • 3/26: Proposals from prospective Design Build Entities (DBE) received

Status Update As of: 3/15/2021

  • RFP due date: 3/19/2021

Status Update As of: 3/1/2021

  • 2/24/2021: RFP has been posted
  • 3/19/2021: Bid due date

Status Update As of: 2/15/2021

  • No update

Status Update As of: 2/1/2021

  • GCC posted project RFQ/P in week of 2/1/2021

Status Update As of: 1/4/2021

  • No update

Status Update As of: 12/21/2020

  • Week of 12/14/2020: Additional securing of acquired property units and fencing material installed

Status Update As of: 12/7/2020

  • Reviewing RFQ/P status
  • Programming complete
  • Reviewing potential delivery method for project
  • Reviewing requests of storage and parking items from Users
  • Feasibility study shared and reviewed with Users
  • Reviewed revised conceptual design proposal with Garfield Campus Leadership
  • Received updated conceptual design proposal from Architect
  • Received revised proposal reflecting more green space; Architect to revisit with estimator and provide new proposal
  • Revising initial conceptual design to add more green space for CDC and faculty/staff use while maintaining 200 additional parking spots
  • Architect to provide 2-phase demolition versus partial demobilization options
  • Received additional fencing on 7/31/2020; installed mesh with GCC logo
  • Architect’s parking / landscape design presented
  • HAZMAT study completed for acquired properties to be demolished
  • Completed Topographical and Underground Utility surveys
  • Completed perimeter fencing of acquired properties; integrated informational content to fencing