Montrose Campus (PDC/Citibank) – Project Update History
Status Update As of: 2/1/2021
- No update
Status Update As of: 1/4/2021
- No update
Status Update As of: 12/7/2020
- Received final Underground/Topographic merged survey
- Received HAZMAT reports
- HAZMAT survey completed on 9/08 and 9/09
- GCC Facilities Construction Team project coordination meetings scheduled to occur bi-weekly starting on 8/13/2020
- HAZMAT reports have been requested for existing buildings
- Internal Kickoff meeting scheduled for 8/13/2020
- Citibank building is currently unoccupied and can be offered as swing space for storage needs of the Verdugo Campus
- Draft PDB-RFP pending review; include bridging documents, programming documents, and Educational Needs Assessment
- Programming Needs Assessment conducted by consulting firm and reviewed by Academic Leadership