Verdugo Campus: Saturday (10/2) to Friday (10/15) – Lane closure of Verdugo Rd. near the walkway bridge area to accommodate utility connection activities to City utility lines for the New Science Building Project to take place from 7:00 AM to 4:00 PM for a period of 12 days. Alternative pathway will be provided for pedestrians to be routed up the walkway bridge; this activity will minimally impede traffic entering or exiting the campus.
Verdugo Campus: Friday (10/15) – Concrete repair for the Sierra Vista Building walkway to take place from 7:00 AM to 3:00 PM. Concrete trucks will enter via Mountain St.; flag persons will be stationed in the area to ensure pedestrian safety and there will be minimal impedance on traffic entering or exiting the campus.
Garfield Campus: Saturday (10/16) – Concrete sawcutting activities to take place near the Parent Support Center, mechanical enclosure, and project construction trailer areas. Barriers will be stationed in the area to ensure traffic and site safety; activities will minimally impede traffic entering or exiting the campus.
Verdugo Campus: Week of Monday (10/25): Assembly of fence to safely enclose the following locations in Parking Lot B – Northwest corner of parking lot (near CA-2 freeway) to house large-size New Science Building (NSB) façade mock-ups and a select area of parking spaces near the hillside to store soil pile-up from the NSB project; the areas will remain fenced in until the Spring of 2023. These activities will impact parking for Parking Lot B.

Garfield Projects

Mariposa Renovation – Project Update History

Status Update As of: 9/20/2021

  • Los Angeles County Health Department approved of completed Café retrofit activities
  • Project pending Division of State Architect (DSA) Certification

Status Update As of: 9/1/2021

  • 9/8: Los Angeles County Health Department inspection of completed Café retrofit activities

Status Update As of: 8/2/2021

  • DSA Certification procedure in progress

Status Update As of: 7/19/2021

  • Café retrofit activities in progress

Status Update As of: 6/21/2021

  • Proposals for Café retrofit scope received and under review

Status Update As of: 5/17/2021

  • Final payment and retention release processing in progress

Status Update As of: 5/03/2021

  • General Contractor to install office light fixtures
  • Close out of punch-list items in progress

Status Update As of: 4/19/2021

  • Los Angeles County Health Department Plan-check comments under review
  • Remaining Café items nearing completion for site punch walk review

Status Update As of: 4/5/2021

  • Final punchlist items nearing completion
  • Filtration system reinstallation in Café in progress
  • HVAC JACE installation complete

Status Update As of: 3/15/2021

  • 3/25: Target date for JACE additions to HVAC system
  • 3/18: Project photos to be taken by Architect
  • Week of 3/15: Anticipating final punchlist items to be completed

Status Update As of: 3/1/2021

  • 3/5/2021: Site walk with Inspector of Record
  • Week of 2/25/2021: Beginning additional HVAC system upgrades with target completion of mid-March

Status Update As of: 2/15/2021

  • No update

Status Update As of: 2/1/2021

  •  Punchlist corrections in progress
  • 2/04/2021: Delivery of final furniture items
  • Remaining receptacle labels and decal installation in progress

Status Update As of: 1/4/2021

  • Fire alarm testing and programming with the Verdugo (main campus) panel in progress
  • Fire alarm and fire sprinkler installations complete
  • Week of 1/18/2021: Target date for completion of air balancing
  • 1st Floor, 2nd Floor, and 3rd Floor renovations complete

Status Update As of: 12/21/2020

  • Executive office relocations in progress
  • Jan-Feb 2021: Anticipated arrival of furniture
  • End of January: Target date for commissioning and final completion of project
  • 12/31/2020: Target substantial completion date for Café
  • 12/18/2020: Substantial completion date for 2nd Floor, 3rd Floor, Room 116, and Room 125

Status Update As of: 12/7/2020

  • Arrival of furniture anticipated in early 2021
  • Site electrical work for 2nd Floor Elevator Smoke Curtain and external ADA doors in progress
  • Scheduling pre-installation meeting of Café equipment with prospective Café vendor in progress; target date for substantial completion late December 2020
  • Carpet installation date TBD
  • Café cabinet fabrication complete
  • Tile, preliminary Fire Alarm, and lighting installations to begin week of 11/16/2020
  • Drywall installation anticipated for completion in the week of 11/16/2020; T-Bar ceiling framing and painting in progress
  • Fire sprinkler and Vinyl Composition Tile (VCT) flooring installation beginning 11/9/2020
  • Engaging vendor for 2nd Floor elevator curtain repair
  • Relocating Mariposa 220 cubicles to renovated Verdugo Campus Library area
  • Tile installation and HVAC ductwork began week of 10/05/2020
  • Drywall installation, HVAC blocking supports, Drywall tape and finish from 303 to 315A, door frame installation, and preliminary electrical work in progress
  • T-Bar ceiling blockings for 1st and 2nd Floor complete
  • New non-load bearing wall framing on 1st Floor of the café complete
  • Ongoing activities include: Framing, electrical, and drywall installation through the next few weeks
  • Began HVAC ductwork on week of 09/21/2020
  • Completed Café concrete slab-on-ground on 09/16/2020
  • Underground plumbing complete
  • Completed non-load bearing wall framing and underground plumbing and inspection on 9/01
  • Demolition of select areas on the 1st, 2nd, and 3rd Floors complete; HVAC demolition in process
  • Beginning processes of non load-bearing walls installations, preliminary electrical installations, underground plumbing, and new HVAC duct work
  • Preconstruction meeting held on 7/27/2020
  • Demolition process began for 2nd Floor and 3rd Floor of building on 7/28/2020
  • 1st Floor demolition started week of 8/3/2020
  • Furniture and equipment located on 1st Floor has been relocated in coordination with ITS