Mariposa Renovation – Project Update History

Status Update As of: 10/04/2021

  • No update

Status Update As of: 9/20/2021

  • Los Angeles County Health Department approved of completed Café retrofit activities
  • Project pending Division of State Architect (DSA) Certification

Status Update As of: 9/1/2021

  • 9/8: Los Angeles County Health Department inspection of completed Café retrofit activities

Status Update As of: 8/2/2021

  • DSA Certification procedure in progress

Status Update As of: 7/19/2021

  • Café retrofit activities in progress

Status Update As of: 6/21/2021

  • Proposals for Café retrofit scope received and under review

Status Update As of: 5/17/2021

  • Final payment and retention release processing in progress

Status Update As of: 5/03/2021

  • General Contractor to install office light fixtures
  • Close out of punch-list items in progress

Status Update As of: 4/19/2021

  • Los Angeles County Health Department Plan-check comments under review
  • Remaining Café items nearing completion for site punch walk review

Status Update As of: 4/5/2021

  • Final punchlist items nearing completion
  • Filtration system reinstallation in Café in progress
  • HVAC JACE installation complete

Status Update As of: 3/15/2021

  • 3/25: Target date for JACE additions to HVAC system
  • 3/18: Project photos to be taken by Architect
  • Week of 3/15: Anticipating final punchlist items to be completed

Status Update As of: 3/1/2021

  • 3/5/2021: Site walk with Inspector of Record
  • Week of 2/25/2021: Beginning additional HVAC system upgrades with target completion of mid-March

Status Update As of: 2/15/2021

  • No update

Status Update As of: 2/1/2021

  •  Punchlist corrections in progress
  • 2/04/2021: Delivery of final furniture items
  • Remaining receptacle labels and decal installation in progress

Status Update As of: 1/4/2021

  • Fire alarm testing and programming with the Verdugo (main campus) panel in progress
  • Fire alarm and fire sprinkler installations complete
  • Week of 1/18/2021: Target date for completion of air balancing
  • 1st Floor, 2nd Floor, and 3rd Floor renovations complete

Status Update As of: 12/21/2020

  • Executive office relocations in progress
  • Jan-Feb 2021: Anticipated arrival of furniture
  • End of January: Target date for commissioning and final completion of project
  • 12/31/2020: Target substantial completion date for Café
  • 12/18/2020: Substantial completion date for 2nd Floor, 3rd Floor, Room 116, and Room 125

Status Update As of: 12/7/2020

  • Arrival of furniture anticipated in early 2021
  • Site electrical work for 2nd Floor Elevator Smoke Curtain and external ADA doors in progress
  • Scheduling pre-installation meeting of Café equipment with prospective Café vendor in progress; target date for substantial completion late December 2020
  • Carpet installation date TBD
  • Café cabinet fabrication complete
  • Tile, preliminary Fire Alarm, and lighting installations to begin week of 11/16/2020
  • Drywall installation anticipated for completion in the week of 11/16/2020; T-Bar ceiling framing and painting in progress
  • Fire sprinkler and Vinyl Composition Tile (VCT) flooring installation beginning 11/9/2020
  • Engaging vendor for 2nd Floor elevator curtain repair
  • Relocating Mariposa 220 cubicles to renovated Verdugo Campus Library area
  • Tile installation and HVAC ductwork began week of 10/05/2020
  • Drywall installation, HVAC blocking supports, Drywall tape and finish from 303 to 315A, door frame installation, and preliminary electrical work in progress
  • T-Bar ceiling blockings for 1st and 2nd Floor complete
  • New non-load bearing wall framing on 1st Floor of the café complete
  • Ongoing activities include: Framing, electrical, and drywall installation through the next few weeks
  • Began HVAC ductwork on week of 09/21/2020
  • Completed Café concrete slab-on-ground on 09/16/2020
  • Underground plumbing complete
  • Completed non-load bearing wall framing and underground plumbing and inspection on 9/01
  • Demolition of select areas on the 1st, 2nd, and 3rd Floors complete; HVAC demolition in process
  • Beginning processes of non load-bearing walls installations, preliminary electrical installations, underground plumbing, and new HVAC duct work
  • Preconstruction meeting held on 7/27/2020
  • Demolition process began for 2nd Floor and 3rd Floor of building on 7/28/2020
  • 1st Floor demolition started week of 8/3/2020
  • Furniture and equipment located on 1st Floor has been relocated in coordination with ITS