Verdugo Projects
Instructional Building & Conference Center – Project Update History
Status Update As of: 1/24/2023
- February 2023: Target timeframe for Division of the State Architect (DSA) plans and specification approval
Status Update As of: 1/10/2023
- Division of the State Architect (DSA) review and comments complete; backcheck scheduling in progress
Status Update As of: 11/15/2022
- 11/28 – 12/05: Anticipated timeline of Division of State Architect (DSA) response of design
- Relocation options of Memorial Oak Tree under review
Status Update As of: 11/01/2022
- Division of the State Architect (DSA) final comments and DSA Approval anticipated November 2022
Status Update As of: 10/04/2022
- No update
Status Update As of: 09/06/2022
- 10/04 – 10/10: Target timeframe of Prequalified Trades review
- Division of the State Architect (DSA) design approval activities ongoing
Status Update As of: 08/23/2022
- Schedule review in progress
- Public procurement review complete
Status Update As of: 08/10/2022
- Pre-qualification and bidding packages under review
Status Update As of: 07/19/2022
- 7/19: Public procurement process meeting and demolition planning scheduled with GCC and General Contractor
- 10/24: Target date for project site mobilization
- Schedule of activities under review
Status Update As of: 07/05/2022
- 10/24: Target date for contractor mobilization
- 11/21: Target date to begin site demolition activities; anticipate 12-week demolition period
- Site logistics plan review in progress
Status Update As of: 06/07/2022
- 6/01: Value engineering options discussion
Status Update As of: 05/17/2022
IBCC Project Swing Space:
- IBCC Project Swing Space at the Civic Auditorium completed
Status Update As of: 05/03/2022
IBCC Building:
- Building material finishing review complete
- Project building options under review
- Project management trailer relocation options under review
IBCC Project Swing Space:
- 5/04: Scheduled date of mechanical inspection for Civic Auditorium project swing space in progress
- Fire Marshall inspection of Civic Auditorium project swing space approved
- Final building safety inspection of Civic Auditorium project swing space in progress; Target estimated completion date 5/15/2022
Status Update As of: 04/18/2022
- 4/18: Target date for Civic Auditorium project swing space Punch List item completion
- Mechanical inspection and permit receipt items for Civic Auditorium project swing space in progress
Status Update As of: 04/04/2022
- 4/08: AC system installation in Civic Auditorium swing space completed
- Project schedule update and review in progress
- Project Furniture, Fixtures, and Equipment (FF&E) matrix review in progress
Status Update As of: 03/21/2022
- Scheduling of Civic Auditorium swing space fire sprinkler sitewalk with contractor and final inspection sign-off with the City of Glendale Fire Marshall in progress
Status Update As of: 03/07/2022
- 3/04: Swing space updates to user group
- 3/07: Data and telecommunications installation for Civic Auditorium swing space completed
- Coordination of final Fire Marshall walkthrough and approval of new and adjusted fire sprinklers for Civic Auditorium swing space in progress
Status Update As of: 02/07/2022
- Furniture, Fixtures, and Equipment (FF&E) protocol timeline updates and milestones with user group in progress
- Project construction management trailer location confirmed with the City of Glendale
- IT/AV item discussions and review in progress
Status Update As of: 01/10/2022
- Furniture, Fixtures, and Equipment (FF&E) proposal engagement and review in progress
Status Update As of: 12/20/2021
- Project schedule updates with General Contractor in progress
- Project logistics planning items and review in progress
- Project construction management trailer location review in progress
- Project responsibility matrix for Furniture, Fixtures, and Equipment (FF&E) in development
Status Update As of: 12/06/2021
- Updated project schedule review in progress
- 95% Construction Document (CD) drawing review in progress
- Project cost estimate of 95% Construction Document (CD) deliverables in progress
Status Update As of: 11/15/2021
- 11/09: Utilities site walk completed
- 11/12: Received underground utilities as-built drawings
- 11/12: Review of draft schedule completed
- 11/19: Target date for 95% Construction Document (CD) submission
- Scheduling of Furniture, Fixtures, and Equipment (FF&E) meetings in progress
Status Update As of: 11/01/2021
- Summer 2022: Target timeline for demolition activities
- 11/2: GCC programs’ swing space site walk
- 11/9: Site logistics plan presentation and walkthrough with GCC Police Department
- 11/11: Due date of project bids for GCC programs’ swing spaces
- End of Feb 2022: Target date for completion of swing spaces of GCC programs
- GCC mark-up notes of construction drawings communicated to Design Team
- Utility potholing complete
Status Update As of: 10/18/2021
- Project site logistics plan presentation with Glendale Community College Police Department in progress; target date – 11/02/2021
- Identifying prospective construction trailer locations in progress
- Furniture, Fixtures, and Equipment item inclusions to overall project schedule in progress
Status Update As of: 10/04/2021
- Week of 10/4: Project schedule review
- 10/7: Underground investigation activities
- 10/8: Site walk for sound mitigation wall complete
- 10/14: Target date for project logistics review with General Contractor
Status Update As of: 9/20/2021
- Hydrant flow test of area complete
- Swing Space Meetings with User Groups complete
- Donation equipment and room names under review
Status Update As of: 9/1/2021
- 9/7: Site walk of future project area and existing Verdugo Gym Expansion Project underground utilities
- Audio and visual scope discussions in progress
- Fire hydrant flow tests near future project area completed
- Swing space planning in progress
- Donation of equipment and prospective room names under review
Status Update As of: 8/2/2021
- 7/31: Fire hydrant flow rate tests completed
- 8/6: FF&E Interior Design meeting
- 8/10: Anticipated date of 100% DD Final Estimate to the District
Status Update As of: 7/19/2021
- 7/15: Site walk of project site completed
- 8/06: Target date for 100% Design Development (DD) estimate reconciliation
Status Update As of: 6/21/2021
- Discussions of 50% DD Final Estimate in progress
- Investigation of utility lines in progress
Status Update As of: 5/17/2021
- 50% Design Development document review and estimating activities in progress
- Additional user group meetings scheduled
Status Update As of: 5/03/2021
- Campus gas load and gas line pressures for prospective building service under review
- General Contractor reviewing drainage systems of project site
- Existing and proposed FF&E and AV equipment lists under review
- Swing space for remaining College District functions and programs currently housed in future project site area under review
Status Update As of: 4/19/2021
- Value engineering activities in progress
- Schedule review in progress
- Prospective locations for gas line PSI testing under review
- 4/20: Geotechnical slope analysis of project site completed
- 5/07: Target date for 50% Design Development (DD) documents
Status Update As of: 4/5/2021
- Geotechnical field percolation testing complete
- Design Development phase detail meetings with User Groups in progress
Status Update As of: 3/15/2021
- Design Development in progress
- Preliminary FF&E schedule provided by consulting entities
- Percolation test results completed
- Geotechnical comments provided by Design Build Entity under review
- Arborist report for greenery relocation received
- 3/11: Mechanical, Electrical, and Plumbing investigations completed
Status Update As of: 3/1/2021
- 2/23/2021: Percolation testing of site complete
- 2/16/2021: Board of Trustees approved presented 100% Schematic Design drawings
- Cost estimate review based Schematic Design in progress
- Awaiting additional Arborist report of site
Status Update As of: 2/15/2021
- No update
Status Update As of: 2/1/2021
- 2/04/2021 – 2/05/2021: Completed additional bore drillings for project site and surrounding area
- 2/16/2021: Schematic Design presentation for Board of Trustees Approval
- Arborist report for surrounding trees of project site in progress
Status Update As of: 1/4/2021
- End of January: Target date for completion of schematic design of project
- 1/11/2021: Scheduled date for remaining 4 bore drillings for project site
Status Update As of: 12/21/2020
- Halfway mark of Schematic Design reached; target completion of Schematic Design – 2/9/2021
- Initial programming and validation phase complete
- 12/16/2020: 5 of 9 borings drilled; remaining borings to be completed on 1/11/2021; results and report anticipated 1/15/2021
- Current and future furniture, fixture, and equipment (FF&E) items under review
Status Update As of: 12/7/2020
- Project estimate review scheduled for 12/10/2020
- Preliminary report of borings drilled received 12/3/2020
- Initial schematic design meetings with User Groups scheduled for the week of 12/14/2020
- Additional User Group meeting with the Culinary Arts Department: completed 11/5/2020
- Drilling of borings on project site completed on 11/11/2020
- Mechanical, Electrical, and Plumbing site walk with the DBE: completed 11/3/2020
- Drafting of Geotechnical survey RFQ/P in progress
- Site and GCC programs walk with DBE and User Groups on 10/20/2020
- Swing space planning meetings and responses in progress
- Currently conducting Program Validation Phase Meetings with User Groups; Initial meeting held on 09/25/2020
- Contract negotiations with selected DBE completed
- Conducted swing space meeting with user groups on 9/10
- Awarding of selected DBE approved by the Board of Trustees on 8/18/2020
- Post-interview Meet and Greet meeting with selected DBE of PCL/SteinbergHart held on 8/6/2020
- Conducted interview with Design Build Entity (DBE) on July 28, 2020
- Proposals of prospective Design Build Entities (DBEs) received on July 22, 2020
- Final Programming Document delivered March 2020
- RFQ responses for Design‐Build procurement received on May 4, 2020