Energy Conservation – Project Update History

Status Update As of: 12/7/2020

  • Administration Window Replacement Project (AWRP)
    • Project has been completed
    • Exterior door hardware, wiring, and staining in progress
    • Final Punch List inspection on 10/26/2020
    • Closing out of Punch List items in progress – window and door items walk-through completed on 09/25/2020
    • Overall Project 97% complete
    • Phase 5 to begin week of 08/17/2020
    • Phase 4 currently in progress
    • Phase 3 complete
    • Phase 1 and Phase 2 complete