The 2025-2035 GCC Facilities Strategic Plan (Abridged) as presented to the Board of Trustees on Nov 19, 2024

Verdugo Projects

Centralized Storage Facility – Project Update History

Project Completion: Design – 95%

Status Update As of:

  • 2/7/2024: No update
  • 1/31/2024: No update

Status Update As of: 2/28/2023 (Last two week’s activities in bold)

  • Project Completion: Design – 50%
  • 2/28: User group meeting to review 50% Construction Documents (CD)

Status Update As of: 1/24/2023

  • 25% Construction Document (CD) in progress

Status Update As of: 1/10/2023

  • Estimated 4-to-5-month DSA Review duration
  • Estimated 9-to-12-month construction duration
  • Awaiting Architect provision of next design steps

Status Update As of: 11/15/2022

  • Mezzanine Option 2 design selected by GCCD

Status Update As of: 11/01/2022

  • Follow up discussions with Architect on design in progress

Status Update As of: 10/04/2022

  • No update

Status Update As of: 09/06/2022

  • No update

Status Update As of: 08/23/2022

  • No update

Status Update As of: 08/10/2022

  • Central storage redesign in progress pending existing inventory assessments

Status Update As of: 07/19/2022

  • Area redesign presented by Architect under review

Status Update As of: 07/05/2022

  • No update

Status Update As of: 06/07/2022

  • Permanent Duplicating & Printing Services location renovation approved
  • Scheduling meeting with design vendor for project area in progress

Status Update As of: 05/17/2022

  • No update

Status Update As of: 05/03/2022

  • No update

Status Update As of: 04/18/2022

  • Coordinating move schedule with vendor for Citibank Building storage area

Status Update As of: 04/04/2022

  • 4/08: Scheduled user group meeting

Status Update As of: 03/21/2022

  • Citibank Building interior demolition for storage needs completed; cleanout status under review
  • Scheduling of user group meeting in progress

Status Update As of: 03/07/2022

  • Programming completed for Duplicating Department
  • New layout, programming requirements for data and electric item discussions in progress

Status Update As of: 02/07/2022

  • Architect completed programming requirements select departments; awaiting proposal

Status Update As of: 01/10/2022

  • Storage coordination review in progress

Status Update As of: 12/20/2021

  • Space design update under Division of the State Architect (DSA) review

Status Update As of: 12/06/2021

  • Coordination with user groups for itemized material lists and storage efforts

Status Update As of: 11/15/2021

  • Architect schedule revision in progress
  • Inventory identification and tagging activities for item relocations in progress

Status Update As of: 11/01/2021

  • 11/2: Architect coordination meeting for design and construction coordination

Status Update As of: 10/18/2021

  • Project and space presentation to Users Groups in progress

Status Update As of: 10/04/2021

  • No update

Status Update As of: 9/20/2021

  • Coordination of Kick-off Meeting in progress

Status Update As of: 9/1/2021

  • Design scope processes in progress

Status Update As of: 8/2/2021

  • Prospective vendor proposal under review

Status Update As of: 7/19/2021

  • No update

Status Update As of: 6/21/2021

  • Central storage assessment and programming proposal from prospective vendor in progress

Status Update As of: 5/17/2021

  • No update

Status Update As of: 5/03/2021

  • No update

Status Update As of: 4/19/2021

  • No update

Status Update As of: 4/5/2021

  • Theatre storage inventory list in progress

Status Update As of: 3/15/2021

  • No update

Status Update As of: 3/1/2021

  • No update

Status Update As of: 2/15/2021

  • No update

Status Update As of: 2/1/2021

  • No update

Status Update As of: 1/4/2021

  • No update

Status Update As of: 12/7/2020

  • 3 Mobile Mini Containers removed (10/20)
  • Coordination of potential rearrangement of existing storage items in progress
  • Received final storage needs assessment in week of 9/02
  • GCC requested architects to include the Health Science Building attic area for electronic conversion/document conversion assessment
  • Storage needs assessment in progress
  • 8,150 sf of centralized district storage has been incorporated in Science Building design