The 2025-2035 Facilities Strategic Plan – DRAFT as presented to the Board of Trustees on July 26, 2024

Montrose Projects

Montrose Campus (PDC/Citibank) – Project Update History

Status Update As of: 2/1/2021

  • No update

Status Update As of: 1/4/2021

  • No update

Status Update As of: 12/7/2020

  • Received final Underground/Topographic merged survey
  • Received HAZMAT reports
  • HAZMAT survey completed on 9/08 and 9/09
  • GCC Facilities Construction Team project coordination meetings scheduled to occur bi-weekly starting on 8/13/2020
  • HAZMAT reports have been requested for existing buildings
  • Internal Kickoff meeting scheduled for 8/13/2020
  • Citibank building is currently unoccupied and can be offered as swing space for storage needs of the Verdugo Campus
  • Draft PDB-RFP pending review; include bridging documents, programming documents, and Educational Needs Assessment
  • Programming Needs Assessment conducted by consulting firm and reviewed by Academic Leadership