Verdugo Projects
San Gabriel Renovations‐Math Department Relocation – Project Update History
8/22/2024:
What’s been done and what is coming up:
- 5/30 to 8/21/24 – Framing – 95%
- 6/5 to 8/22/204 – Rough Electrical – 90%
- 7/3 to 8/23/24 – Rough Low Voltage/ Fire Alarm – 90%
- 7/12 to 9/3/24 – Rough HVAC -35%
- 7/15 to 9/6/24 – Gypsum Board – 65%
- 8/27 to 9/18 – Painting
8/14/2024:
What’s been done and what is coming up:
- 5/30 to 8/7/24 – Framing – 95%
- 6/5 to 8/8/204 – Rough Electrical – 90%
- 7/3 to 8/9/24 – Rough Low Voltage/ Fire Alarm – 90%
- 7/12 to 8/21/24 – Rough HVAC -35%
- 7/15 to 8/27/24 – Gypsum Board – 65%
- 7/24 to 8/8/24 – Demo additional Plumbing Work – 80%
- 7/29 to 8/7/24 – Delay due to RFI #36 07/26/2024 and PCO 14
- 8/8 to 8/15/24 – Structural Steel for Sliding Glass Panel Partitons
- 8/27 to 9/6 – Painting
Project Completion: Designing – 100%
Status Update As of: 2/7/2024
What’s been done and what is coming up:
Design Page Turn Scheduled with HMC on 2/01/24
Gafcon/GCC to revised project budget
GCC to review final Bidding Documents
1/31/2024:
What’s been done and what is coming up:
Design Page Turn Scheduled with HMC on 2/01/24
Gafcon/GCC to revised project budget
GCC to review final Bidding Documents
Status Update As of: 1/24/2023
- February 2023: Target timeframe for Division of the State Architect (DSA) plans and specification approval
- Bluebeam comments have been completed by Division of the State Architect (DSA)
- Project Manager and Architect scheduling constructability backcheck review
Status Update As of: 1/10/2023
- Project Manager proposal for project services under review
- Division of the State Architect (DSA) comments complete of project documentation
- Information of prospective laptops for use in labs under review
- Project Manager and Architect scheduling of constructability backcheck review in progress
Status Update As of: 11/15/2022
- Project Management team reassessing construction cost estimate update for review
- Pending Division of State Architect (DSA) approval of design; submitted 10/26
Status Update As of: 11/01/2022
- Construction cost updates under review
- Discussion of project bidding timeline in progress
- Division of the State Architect (DSA) final comments and DSA Approval anticipated November 2022
Status Update As of: 10/04/2022
- 10/26: Target date for Architect to submit Division of the State Architect (DSA) drawing set for constructability review and backcheck of comments
- Estimate of construction cost changes under review
Status Update As of: 09/06/2022
- Week of 9/05: Target timeframe for constructability review response discussions
- 10/13: Target date for project design submission to Division of the State Architect (DSA)
Status Update As of: 08/23/2022
- 8/23: Project constructability review discussions
- 9/06: Target date of DSA submission pending comment and cost review
Status Update As of: 08/10/2022
- Week of 8/09: Target date for Project Manager to complete project constructability review
Status Update As of: 02/07/2022
- Design on hold until third quarter of 2022
Status Update As of: 01/10/2022
- Wireless beta testing complete; awaiting end user feedback
Status Update As of: 12/20/2021
- No update
Status Update As of: 12/06/2021
- Contractor proposal for furnishings in progress
Status Update As of: 11/15/2021
- No update
Status Update As of: 11/01/2021
- Week of 11/1: Anticipated charging cart station acquisitions
- Beta test of Math and Science computer labs functionality for wireless configuration complete; coordinating compatible furniture options in progress
Status Update As of: 10/18/2021
- Week of 10/18: Target timeline for charging cart station acquisition
- Wireless beta test development discussions and feedback with GCC IT Department in progress
Status Update As of: 10/04/2021
- No update
Status Update As of: 9/20/2021
- No update
Status Update As of: 9/1/2021
- November 2021: Target date for San Gabriel wireless beta test recommendations
Status Update As of: 8/2/2021
- No Update
Status Update As of: 7/19/2021
- Awaiting design progression and technical comments for beta testing
Status Update As of: 6/21/2021
- Planning of 3 phase WiFi beta testing in progress
Status Update As of: 5/17/2021
- No update
Status Update As of: 5/03/2021
- No update
Status Update As of: 4/19/2021
- No update
Status Update As of: 4/5/2021
- No update
Status Update As of: 3/15/2021
- No update
Status Update As of: 3/1/2021 (Last two week’s activities in bold)
- Preparations for WIFI beta test in progress
Status Update As of: 2/15/2021
- No update
Status Update As of: 2/1/2021
- No update
Status Update As of: 1/4/2021
- No update
Status Update As of: 12/7/2020
- WiFi beta test design in progress; target date for completion – end of June 2021
- 1/11/2021: Target date to receive back-check of Constructibility Review comments and updated cost estimate from Construction Manager
- 12/18/2020: 90% Construction Documents and review comments received
Status Update As of: 12/7/2020
- 90% Construction Documents and review comments anticipated 12/18/2020
- 50% Construction Documents and specifications received from the Architect
- The Architect completed door survey and provided cost estimate
- AT107 under consideration as model for wireless design conversion
- Target date for DSA submission: 12/18/2020
- 50% Construction Documents submission in progress; target date 11/13/2020
- Constructibility and cost estimate verification reviews submitted on 10/23/2020
- Requesting proposal for wireless network engineering design in process
- Information Technology System meeting to be scheduled related to prospective wireless option approach
- Scheduling cost estimate review with General Contractor after receipt of Design Document set
- Conducted presentation for User Groups on 09/25/2020
- General Contractor provided updated cost estimate in week of 09/21/2020
- Architect design schedule revised to show continuous effort through DSA submission –
- Project Manager scheduling next User Group Meeting to review Design Development progress by the Architect
- General Contractor provided updated cost estimate on 9/08 after value engineering cost exercise with team
- San Gabriel 2nd Floor Renovation design efforts restarted week of 8/10/2020
- Architect design schedule anticipates completion of Design Development (DD) by end of September 2020
- Construction Manager (CM) to issue project schedule for architects to target Design Development restart date
- Project Manager (PM) and CM provided 25% DD scope/estimate reconciliation
- Architect submitted 25% Design Development (DD) plans to PM and CM