The 2025-2035 GCC Facilities Strategic Plan (Abridged) as presented to the Board of Trustees on Nov 19, 2024

Verdugo Projects

Centralized Storage Facility

Project Team

Project Manager Silva Sorkazian/Clifford Gimbert, Glendale Community College
Construction Manager TBD
Architect of Record Joe Monfreda, 19-Six Architects
Inspector of Record Tony Castiglioni, VIS Vital Inspection Services Inc.

Description

The Centralized Storage Facility will provide space for district-wide, long-term storage of documents, furniture, and equipment. It will replace the temporary storage containers currently found in multiple locations across the Verdugo Campus, as well as the basement storage in the Administration Building. The Centralized Storage Facility will be centrally located in the Science Building.

Updates

8/26/2024:

  • *PROJECT ON HOLD*
  • DSA Approved 5/23/2024 A#03-123613 good for 4 years

Status

Construction 99%