The new five-story Science Building will help meet the demand for instruction in the biological and physical sciences, which require specialized, state-of-the-art teaching and laboratory spaces. The new building will replace insufficiently sized and outdated facilities in the San Gabriel, Arroyo Seco, and Camino Real buildings and help align Glendale Community College’s course offerings with the State’s focus on STEM and research-based instruction. The new labs will be designed to comply with current operational safety standards, including those of the American Chemical Society, the highest authority for collegiate chemistry labs. The Science Building will be a signature building for the College and feature strong circulation links to the San Gabriel, Health Sciences, and Camino Real buildings. For more information on the project, CLICK HERE.

Updates

Project Completion: Construction – 71%

Status Update As of: 2/28/2023 (Last two week’s activities in bold)

  • 2/03: Public Bid Notification for Phase II scope published; due 2/28/2023
  • 2/03: January schedule update under review
  • 2/13: Lab Casework Changes approved by Division of the State Architect (DSA)
  • 2/22: Connection of Advanced Technology Building roof drain lines to New Science Building site drainage completed
  • 2/23: Commissioning Agent completed site observation of work in place
  • 2/28: Due date for copper/fiber data cabling Request for Proposal (RFP)

Status

Construction 85%

Project Team

Project Manager John Leopardi, Gafcon, Inc.
Construction Manager John Theis, DPR Construction
Architect of Record Sean Rosebrugh, HMC Architects
Inspector of Record Ted Lamoureux, TYR, Inc.