Verdugo Campus: Dec 06 (T) – Dec 14 (W) – Trenching activities near south Auditorium Building entrance for Central Plant 1 Expansion Project. Access to southern double-door exit impacted; signage for alternative paths of travel is provided.
Verdugo Campus: Dec 09 (F) – Steel delivery in Lot H for Central Plant 1 Expansion Project to take place at 7:00 AM. Trucks will enter the site via the Circle Drive gate entrance on N. Verdugo Rd; area will be taped off.
Verdugo Campus: Dec 13 (T) – Dec 14 (W) – Crane mobilization and steel placement for Central Plant 1 Expansion Project. Access to Lot H parking will be impacted.

Verdugo Projects

San Gabriel Renovations‐Math Department Relocation

Description

The second floor of the San Gabriel Building will be renovated to accommodate the relocation of the Math Discovery Center and classrooms from the Arroyo Seco building. This project also includes the reorganization of science and math instructional and support space in the San Gabriel and Camino Real buildings. These buildings will undergo upgrades to extend their lifespan and implement improvements that will achieve campus-wide objectives for accessibility, sustainability, energy efficiency, signage and wayfinding, and safety and security.

Description

Project Completion: Designing – 95%

Status Update As of: 11/15/2022 (Last two week’s activities in bold)

  • Project Management team reassessing construction cost estimate update for review
  • Pending Division of State Architect (DSA) approval of design; submitted 10/26

Status

Designing 95%

Project Team

Project Manager John Leopardi, Gafcon, Inc.
Construction Manager John Theis, DPR Construction
Architect of Record Sean Rosebrugh, HMC Architects
Inspector of Record Ted Lamoureux, TYR, Inc.