Verdugo Projects

San Gabriel Renovations‐Math Department Relocation

Description

The second floor of the San Gabriel Building will be renovated to accommodate the relocation of the Math Discovery Center and classrooms from the Arroyo Seco building. This project also includes the reorganization of science and math instructional and support space in the San Gabriel and Camino Real buildings. These buildings will undergo upgrades to extend their lifespan and implement improvements that will achieve campus-wide objectives for accessibility, sustainability, energy efficiency, signage and wayfinding, and safety and security.

Description

  • 50% Construction Documents and specifications received from the Architect
  • The Architect completed door survey and provided cost estimate
  • AT107 under consideration as model for wireless design conversion
  • Target date for DSA submission: 12/18/2020
  • 50% Construction Documents submission in progress; target date 11/13/2020
  • Constructability and cost estimate verification reviews submitted on 10/23/2020
  • Requesting proposal for wireless network engineering design in process
  • Information Technology System meeting to be scheduled related to prospective wireless option approach
  • Scheduling cost estimate review with General Contractor after receipt of Design Document set
  • Conducted presentation for User Groups on 09/25/2020
  • General Contractor provided updated cost estimate in week of 09/21/2020
  • Architect design schedule revised to show continuous effort through DSA submission –
  • Project Manager scheduling next User Group Meeting to review Design Development progress by the Architect
  • General Contractor provided updated cost estimate on 9/08 after value engineering cost exercise with team
  • San Gabriel 2nd Floor Renovation design efforts restarted week of 8/10/2020
  • Architect design schedule anticipates completion of Design Development (DD) by end of September 2020
  • Construction Manager (CM) to issue project schedule for architects to target Design Development restart date
  • Project Manager (PM) and CM provided 25% DD scope/estimate reconciliation
  • Architect submitted 25% Design Development (DD) plans to PM and CM

Status

Designing 30%

Project Team

Project Manager John Leopardi, Gafcon, Inc.
General Contractor John Theiss, DPR Construction
Architect of Record Sean Rosebrugh, HMC Architects
Inspector of Record TBD