Verdugo Campus: Saturday (10/2) to Friday (10/15) – Lane closure of Verdugo Rd. near the walkway bridge area to accommodate utility connection activities to City utility lines for the New Science Building Project to take place from 7:00 AM to 4:00 PM for a period of 12 days. Alternative pathway will be provided for pedestrians to be routed up the walkway bridge; this activity will minimally impede traffic entering or exiting the campus.
Verdugo Campus: Friday (10/15) – Concrete repair for the Sierra Vista Building walkway to take place from 7:00 AM to 3:00 PM. Concrete trucks will enter via Mountain St.; flag persons will be stationed in the area to ensure pedestrian safety and there will be minimal impedance on traffic entering or exiting the campus.
Garfield Campus: Saturday (10/16) – Concrete sawcutting activities to take place near the Parent Support Center, mechanical enclosure, and project construction trailer areas. Barriers will be stationed in the area to ensure traffic and site safety; activities will minimally impede traffic entering or exiting the campus.
Verdugo Campus: Week of Monday (10/25): Assembly of fence to safely enclose the following locations in Parking Lot B – Northwest corner of parking lot (near CA-2 freeway) to house large-size New Science Building (NSB) façade mock-ups and a select area of parking spaces near the hillside to store soil pile-up from the NSB project; the areas will remain fenced in until the Spring of 2023. These activities will impact parking for Parking Lot B.

Verdugo Projects

San Gabriel First Floor ‐ Disabled Students Programs and Services (DSPS) Renovation

Description

Space on the first floor of the San Gabriel Building is being designed to become the campus’ new office for Disabled Students Programs and Services (DSPS). This location on the ground floor near the Access bus stop improves access for students with mobility challenges. The project expands testing and assessment space, as well as office space, for DSPS personnel.

Updates

Project Completion: Designing – 35%

Status Update As of: 10/04/2021 (Last two week’s activities in bold)

  • 10/7: Target date for advisement on Addendum 1 to Division of State Architect (DSA) approved plans

Status

Designing 35%

Project Team

Project Manager Silva Sorkazian, Glendale Community College
General Contractor TBD
Architect of Record Rita Carter, Little Architects
Inspector of Record Tony Castiglioni, VIS Vital Inspection Services Inc.