Verdugo Campus: Saturday (10/2) to Friday (10/15) – Lane closure of Verdugo Rd. near the walkway bridge area to accommodate utility connection activities to City utility lines for the New Science Building Project to take place from 7:00 AM to 4:00 PM for a period of 12 days. Alternative pathway will be provided for pedestrians to be routed up the walkway bridge; this activity will minimally impede traffic entering or exiting the campus.
Verdugo Campus: Friday (10/15) – Concrete repair for the Sierra Vista Building walkway to take place from 7:00 AM to 3:00 PM. Concrete trucks will enter via Mountain St.; flag persons will be stationed in the area to ensure pedestrian safety and there will be minimal impedance on traffic entering or exiting the campus.
Garfield Campus: Saturday (10/16) – Concrete sawcutting activities to take place near the Parent Support Center, mechanical enclosure, and project construction trailer areas. Barriers will be stationed in the area to ensure traffic and site safety; activities will minimally impede traffic entering or exiting the campus.
Verdugo Campus: Week of Monday (10/25): Assembly of fence to safely enclose the following locations in Parking Lot B – Northwest corner of parking lot (near CA-2 freeway) to house large-size New Science Building (NSB) façade mock-ups and a select area of parking spaces near the hillside to store soil pile-up from the NSB project; the areas will remain fenced in until the Spring of 2023. These activities will impact parking for Parking Lot B.

Verdugo Projects

New Science Building and Ancillary Projects

Description

The new five-story Science Building will help meet the demand for instruction in the biological and physical sciences, which require specialized, state-of-the-art teaching and laboratory spaces. The new building will replace insufficiently sized and outdated facilities in the San Gabriel, Arroyo Seco, and Camino Real buildings and help align Glendale Community College’s course offerings with the State’s focus on STEM and research-based instruction. The new labs will be designed to comply with current operational safety standards, including those of the American Chemical Society, the highest authority for collegiate chemistry labs. The Science Building will be a signature building for the College and feature strong circulation links to the San Gabriel, Health Sciences, and Camino Real buildings. For more information on the project, CLICK HERE.

Updates

Project Completion: Construction – 41%

Status Update As of: 10/04/2021 (Last two week’s activities in bold)

  • 10/25: Target completion date of foundation pile activities
  • Construction Manager submission of lane closure graphics and permit requests to City of Glendale complete
  • Construction Manager provision of sitework phasing graphic plans in progress
  • Building Information Modeling (BIM) model approved for project 1st Floor

Status

Construction 41%

Project Team

Project Manager John Leopardi, Gafcon, Inc.
Construction Manager John Theis, DPR Construction
Architect of Record Sean Rosebrugh, HMC Architects
Inspector of Record Ted Lamoureux, TYR, Inc.