Verdugo Campus: Jan 27 (F) – Planned crane usage activities for PE Student Locker Building Project to take place over a period of two weeks. Vehicles will enter the site via Lot E entrance on Mountain St.

Verdugo Projects

Centralized Storage Facility

Description

The Centralized Storage Facility will provide space for district-wide, long-term storage of documents, furniture, and equipment. It will replace the temporary storage containers currently found in multiple locations across the Verdugo Campus, as well as the basement storage in the Administration Building. The Centralized Storage Facility will be centrally located in the Science Building.

Updates

Project Completion: Design – 20% 

Status Update As of: 1/24/2023 (Last two week’s activities in bold)

  • 25% Construction Document (CD) in progress

Status

Design 20%

Project Team

Project Manager Silva Sorkazian, Glendale Community College
General Contractor TBD
Architect of Record Joe Monfreda, 19-Six Architects
Inspector of Record TBD