Centralized Storage Facility
Description
The Centralized Storage Facility will provide space for district-wide, long-term storage of documents, furniture, and equipment. It will replace the temporary storage containers currently found in multiple locations across the Verdugo Campus, as well as the basement storage in the Administration Building. The Centralized Storage Facility will be centrally located in the Science Building.
Updates
Project Completion: Design – 20%
Status Update As of: 1/24/2023 (Last two week’s activities in bold)
- 25% Construction Document (CD) in progress
Status
Project Team
Project Manager | Silva Sorkazian, Glendale Community College |
General Contractor | TBD |
Architect of Record | Joe Monfreda, 19-Six Architects |
Inspector of Record | TBD |