Verdugo Campus: Dec 06 (T) – Dec 14 (W) – Trenching activities near south Auditorium Building entrance for Central Plant 1 Expansion Project. Access to southern double-door exit impacted; signage for alternative paths of travel is provided.
Verdugo Campus: Dec 09 (F) – Steel delivery in Lot H for Central Plant 1 Expansion Project to take place at 7:00 AM. Trucks will enter the site via the Circle Drive gate entrance on N. Verdugo Rd; area will be taped off.
Verdugo Campus: Dec 13 (T) – Dec 14 (W) – Crane mobilization and steel placement for Central Plant 1 Expansion Project. Access to Lot H parking will be impacted.

Verdugo Projects

Kinesiology and Vaquero Athletic Complex

Description

The Verdugo Gymnasium was upgraded with a seismic retrofit and expansion to modernize the facility and bring it into compliance with current codes. The project includes the addition of new locker room facilities, an auxiliary gym, and modern Title IX-compliant spaces to support the physical education and athletics programs. Other features include adding elevator access between floors; modernizing or replacing poorly functioning building systems such as plumbing, drainage, heating, and ventilation; and a number of outdoor upgrades, including a shaded space that can accommodate a variety of fitness activities, accessible paths of travel to Sartoris Field, and public restrooms and a concession stand to serve spectators at the field.

Update

Project Completion: Under Construction – 99%

Status Update As of: 11/15/2022 (Last two week’s activities in bold)

  • Kinesiology & Vaquero Athletic Complex – Under Construction 99%
    • 11/15: Light poles on fire lane installed
    • Project close out and Punch List activities ongoing
    • Vendor wall pad vinyl samples will be submitted for review
    • Portable Volleyball System replacement pads installed
  • PE Student Locker & Shower Building
    • Second concrete placement to be scheduled

Status

Under Construction 99%

Project Team

Project Manager Jim Youngblood, Gafcon, Inc.
General Contractor Robert Abolian, The Nazerian Group (TNG)
Architect of Record Monisha Adnani, 19-Six Architects
Inspector of Record Tony Castiglioni, VIS Vital Inspection Services Inc.

Video