Verdugo Campus: Saturday (10/2) to Friday (10/15) – Lane closure of Verdugo Rd. near the walkway bridge area to accommodate utility connection activities to City utility lines for the New Science Building Project to take place from 7:00 AM to 4:00 PM for a period of 12 days. Alternative pathway will be provided for pedestrians to be routed up the walkway bridge; this activity will minimally impede traffic entering or exiting the campus.
Verdugo Campus: Friday (10/15) – Concrete repair for the Sierra Vista Building walkway to take place from 7:00 AM to 3:00 PM. Concrete trucks will enter via Mountain St.; flag persons will be stationed in the area to ensure pedestrian safety and there will be minimal impedance on traffic entering or exiting the campus.
Garfield Campus: Saturday (10/16) – Concrete sawcutting activities to take place near the Parent Support Center, mechanical enclosure, and project construction trailer areas. Barriers will be stationed in the area to ensure traffic and site safety; activities will minimally impede traffic entering or exiting the campus.
Verdugo Campus: Week of Monday (10/25): Assembly of fence to safely enclose the following locations in Parking Lot B – Northwest corner of parking lot (near CA-2 freeway) to house large-size New Science Building (NSB) façade mock-ups and a select area of parking spaces near the hillside to store soil pile-up from the NSB project; the areas will remain fenced in until the Spring of 2023. These activities will impact parking for Parking Lot B.

Verdugo Projects

Athletics and Kinesiology Expansion and Seismic Retrofitting

Description

The Verdugo Gymnasium will undergo a seismic retrofit and expansion to modernize the facility and bring it into compliance with current codes. The project, which is under construction, includes the addition of new locker room facilities, an auxiliary gym, and modern Title IX-compliant spaces to support the physical education and athletics programs. Other features include adding elevator access between floors; modernizing or replacing poorly functioning building systems such as plumbing, drainage, heating, and ventilation; and a number of outdoor upgrades, including a shaded space that can accommodate a variety of fitness activities, accessible paths of travel to Sartoris Field, and public restrooms and a concession stand to serve spectators at the field.

Update

Project Completion: Under Construction – 89%

Status Update As of: 10/04/2021 (Last two week’s activities in bold)

  • Increment II: Under Construction
    • 10/2: Scaffolding removal complete
    • Fire water line trenching in progress
    • Start of tile installation on lower-level bathroom and locker rooms
    • Painting of New Gym ceiling and walls complete
    • Building of storage room walls in progress
    • Upper-level offices ceiling tile installation in progress
    • Clay tile roofing installation in progress
    • Concrete footings for wheelchair lift and stairs in the Concession Stand area complete
    • Additional locker room and shower building configurations submitted to Division of State Architect (DSA) for review
    • Graphics received and conducted final finishing user group presentation

Status

Under Construction 89%

Project Team

Project Manager Michael Wykoff, Gafcon, Inc.
General Contractor Robert Abolian, The Nazerian Group (TNG)
Architect of Record Monisha Adnani, 19-Six Architects
Inspector of Record Tony Castiglioni, VIS Vital Inspection Services Inc.