Verdugo Projects
San Gabriel Renovations‐Math Department Relocation
Project Team
Project Manager | Silva Sorkazian/Clifford Gimbert, Glendale Community College |
Construction Manager | Clifford Gimbert, Glendale Community College |
Architect of Record | Sean Rosebrugh, HMC Architects |
Inspector of Record | Tony Castiglioni, VIS Vital Inspection Services Inc. |
Description
The second floor of the San Gabriel Building will be renovated to accommodate the relocation of the Math Discovery Center and classrooms from the Arroyo Seco building. This project also includes the reorganization of science and math instructional and support space in the San Gabriel and Camino Real buildings. These buildings will undergo upgrades to extend their lifespan and implement improvements that will achieve campus-wide objectives for accessibility, sustainability, energy efficiency, signage and wayfinding, and safety and security.
Updates
12/11/2024:
- Signage, Fire Alarm, Data, Lighting – 100%
- Finish Elect & Acoustical Ceilings Tiles – 95%
- Doors & Hardware – 90%