DPR working on Saturday, May 6th starting at 7:00 am on interior framing/drywall/taping.
Verdugo Projects
Central Plant #1 Expansion
Description
This project anticipates expanding the Central Plant from its current approximate 500-ton capacity to an approximate 1500 ton capacity in anticipation of the construction of the Science Building and the David Viar Performing and Media Arts Center. The existing chillers lack both the capacity and efficiency to provide the necessary cooling for these two new buildings.
Updates
Project Completion: Under Construction – 95%
Status Update As of: 2/28/2023 (Last two week’s activities in bold)
- 2/07: Flushing of cooling towers complete
- 2/07: Installed louvers at screen wall
- 2/10: Startup of all three chillers
- 2/13: Removal of temporary chiller hoses complete
- 2/13: Removal of chiller hose scaffolding complete
- 2/13: Removal of temporary chillers complete
- 2/13: Commissioning startup on site
- 2/14: Removal of temporary electricity for temporary chillers complete
- 2/18: Concrete cutting at dogleg to AU 04 complete
- 2/18: Pot holing at switch back complete
- 2/27: Pot holing report received
Status
Project Team
Project Manager | Jim Youngblood, Gafcon, Inc. |
Construction Manager | John Theis,DPR Construction |
Architect of Record | Sean Rosebrugh,HMC Architects |
Project Design Engineer | Steve Yanke,AEI |
Inspector of Record | TBD |