The 2025-2035 Facilities Strategic Plan – DRAFT as presented to the Board of Trustees on July 26, 2024
Montrose Projects
Montrose Campus (PDC/Citibank)
Description
This project will complete the process of adapting the existing Professional Development Center (PDC) building for educational use, as well as adapting and integrating the recently acquired commercial property that is located on the adjacent parcel in Glendale’s historic Montrose Town Center. Signage will also be upgraded to make an instant visual connection with the architectural styles of the Verdugo and Garfield Campuses, while maintaining the historic charm of Montrose Town Center.
Updates
Project Completion: Programming Complete – 15% (Project on hold as of 01/29/2021)
Status
Project Team
Project Manager | Silva Sorkazian, Glendale Community College |
General Contractor | TBD |
Architect of Record | TBD |
Inspector of Record | TBD |